Vinters Global Networks
Kent, UK

Overall POP Status

Network Connectivity

Power Systems

Support Systems
Frankfurt, DE

Overall POP Status

Network Connectivity

Power Systems

Support Systems
New York, USA

Overall POP Status

Network Connectivity

Power Systems

Support Systems

- Service OK

- Intermittent/Partial Outages

- Mass Service Impacting/Critical Issues
Network Status Notes
| 2026-02-03 16:06:51 | |
| | The fault has now been confirmed as cleared by the provider following a cold restart of a WSS card. The fibre provider has confirmed they will issue a full RFO in due course and will plan any required scheduled maintenance for future prevention of re-occurrence. |
|
| 2026-02-03 15:27:31 | |
| | The Ciena and Fibre engineers have found a fault in the fibre amplifier and are arranging a replacement. We saw the connection briefly come back and then go down again so have shut our transit links on the fibre until the all clear to avoid any flapping of the connection. |
|
| 2026-02-03 12:05:52 | |
| | We have been advised by the fibre provider that a Ciena technician has been deployed to 8-9 Harbour Exchange to work with their engineer to resolve the fault. The current ETA is 15:30 however this may change dependent on initial investigations from the engineer. |
|
| 2026-02-03 09:55:17 | |
| | We have been advised the fibre fault is in the London area and engineers at the vendor and fibre provider have been engaged to investigate further. We are currently awaiting further information and an ETA for fix. |
|
| 2026-02-03 08:55:38 | |
| | We have monitored a local fibre fault on one of our diverse feeds into the Maidstone data centre. Traffic has been automatically re-routed via other fibre links and a fault has been raised with the provider. We are currently awaiting further information on the fault from the provider and an ETA for a fix. |
|